Leeds Train Station 2017

Leeds

Installation of internal graphics

Working close to the electrified overhead lines and in areas that were open to the public 24 hours meant managing the works was highly sensitive.

An extremely detailed risk assessment and method statement was prepared and went through a series of amendments before all the parties involved were satisfied.

All the works were completed within very tight times starting at midnight and having to be

completed by 5am. During this short window each night we would need to set up a full run

of chapter eight barriers and bring the access machine into the station from the service yard.

As we only had three hours a night to actually apply graphics, the job took over a week to

complete.

We applied self adhesive graphics along four elevations working over the ticket barriers and various other obstacles.

The finished result transformed what was an old and dull looking area into a bright and highly

visible “Welcome to Yorkshire” themed fascia.